12 week update

5th August


Our original SS has returned from parental leave, and has given us the upcoming schedule for the next couple of weeks, looks like its all steam ahead, the weather has been co-operating which is nice, just need the rain to stay away for another 2-3 weeks and everything that needs to be completed in "Dry weather" should be done. We were ecstatic to be told the build is due to be completed Mid-October! gives us just enough time to sort out moving, enrolling the kids into new schools and also gives us a couple of months to settle and set up our new home ready for Christmas! A mid October finish also means our two-storey build would have only taken 22 weeks. fingers crossed it all stays on schedule. Water proofing, and render to be done next week.