Bathroom tiling

7th September

The Tilers have been busy...There was a slight hiccup with the extra tiles that were ordered and delivered as the tiler needed 300x300 and the 450x450 arrived, all was sorted in the end though. We also saw (through a photo the tiler sent) that they had installed soap holders even though we have niches?! The tiler has assured that they will be removed, Luckily we spotted this before the tiling and grout had been completed. SS has advised fitout is due to start next wednesday.

First photo of the facade with the garage door down

Powder Room

Ensuite

Main Bathroom

Kitchen/Hallway

Bathroom

Study



Ensuite (powder room tile also)

Main Bathroom