Time Line


28th February-Colour Selections
27th March-Council and Covenant Approval
13th May-Site Cut, Pierring
23rd May-Draining, Plumbing, Slab
3rd June-Frames Started
12th June-Fascias and Gutters
expected dates…
15th June-Roof starts approx. 1 week
25th June- Wrapping completed
26th June-Doors, Windows,Rough in of pumbing and electrical
9th July-2nd story wrap completed
15th July-Lower roof due to be completed
17th July-Insulation to be installed
21st July-Plasterers and Bricks start. take 2 weeks
Followed by rendering, cladding, stairs, and waterproofing.